Laundry plant
Basic information
Basic information
bed sheets: 1000pcs
2.working time:10 hours per day
2.working time:10 hours per day
Calculate:
Bed sheet: 0.8KG×1000=800KG
Quilt cover;1.3KG×1000=1300KG
Pillow cover: 0.3KG×1000=300KG
Towel: 0.2KG×1000=200KG
Bath towel:0.4KG×1000=400KG
In total:
Washing quantity per day: (800+1300+300+200+400)=3000KG
80% business rate: 3000*80%=2400kg
Washing 10 hours per day: 2400KG÷10h=240KG/h
Quilt cover;1.3KG×1000=1300KG
Pillow cover: 0.3KG×1000=300KG
Towel: 0.2KG×1000=200KG
Bath towel:0.4KG×1000=400KG
In total:
Washing quantity per day: (800+1300+300+200+400)=3000KG
80% business rate: 3000*80%=2400kg
Washing 10 hours per day: 2400KG÷10h=240KG/h
Washing machine
Washing quantity:2400kg/day
working time:10 hours per day, 240kg per hour
working time:10 hours per day, 240kg per hour
XGQ-100F | Fully automatic washing machine | 2pc |
XGQ-50F | Fully automatic washing machine | 1pc |
HG-100 | Fully automatic tumble dryer | 1pc |
HG-50 | Fully automatic tumble dryer | 1pc |
YP38030 | 3000mm flatwork ironer | 1pc |
YTT-A | Ironing table | 1pc |